Pages

Thursday, March 31, 2011

Trends in Nunn-McCurdy Cost Breaches for Major Defense Acquisition Programs


Trends in Nunn-McCurdy Cost Breaches for Major Defense Acquisition Programs


Statement of Michael J. Sullivan, GAO Director for Acquisition and Sourcing Management, before the Committee on Homeland Security and Governmental Affairs, Subcommittee on Federal Financial Management, Government Information, Federal Services and International Security, United States Senate; March 29, 2011
This testimony discusses tools available to minimize Department of Defense (DOD) cost overruns and our recent work on the Nunn-McCurdy process.
This statement focuses on (1) trends in Nunn-McCurdy breaches, (2) factors that may be responsible for these trends, (3) changes DOD is making or proposing to make to the Nunn-McCurdy process, and (4) other tools DOD can use to minimize cost overruns. This testimony includes information from our March 2011 report on Nunn-McCurdy breaches, which is being released today.
Since 1997, there have been 74 Nunn-McCurdy breaches involving 47 major defense acquisition programs. There were a larger number of breaches in 2001, 2005, 2006, and 2009, which coincides with new statutory requirements or changes presidential administration.
As a result of Congress requiring DOD to measure cost growth against the original baseline estimate, the number of breaches reported increased in 2005 and 2006. The number of breaches was also high in 2001 and 2009-- the first years of new presidential administrations. During both transitions, no annual comprehensive Selected Acquisition Reports (SAR) were submitted, which, along with other factors, may have affected when breaches were reported.
Nunn-McCurdy breaches are often the result of multiple, interrelated factors. Our analysis of DOD data and SARs showed that the primary reasons cited for the unit cost growth that led to Nunn-McCurdy breaches were engineering and design issues, schedule issues, and quantity changes. For example, we reported in 2003 that the Space Based Infrared System High program began with immature technologies and was based on faulty and overly optimistic assumptions about software reuse and productivity levels, the benefits of commercial practices, management stability, and the level of understanding of requirements. The program has breached four times.
A large number of programs that breached also cited revised estimates, due in part to changing assumptions; requirements changes; and economic changes, such as labor and overhead rates, as factors that contributed to the breaches.
DOD has instituted a process to provide earlier warning of potential Nunn-McCurdy breaches and plans to propose changes to the Nunn-McCurdy process to reduce several statutory requirements for breaches caused by quantity changes. Specifically, the Joint Staff has implemented a process to provide an earlier evaluation of the factors that are contributing to cost growth so that programs can take mitigating actions before experiencing a significant Nunn McCurdy breach.
This new process has merit, as our analysis shows that nearly 40 percent of Nunn-McCurdy breaches occurred after a production decision had been made--when a program has fewer options for restructuring. DOD plans to propose a legislative amendment to reduce several statutory requirements added in 2009 for Nunn-McCurdy breaches when it determines that a breach was caused primarily by quantity changes that were unrelated to poor performance.
According to DOD, not all breaches are indicators of poor performance because quantity reductions or capabilities added to a program after it begins can affect unit cost. The Nunn-McCurdy process can be a useful mechanism for holding programs accountable for cost growth and restructuring them in the wake of cost growth; however, its effect is limited because, in general, programs have already experienced significant problems by the time it is triggered.
It is not realistic to expect cost growth to be entirely preventable, but it can be significantly reduced. To put programs in a position to minimize the risk of cost growth, DOD must use the tools available to it to establish programs in which there is a match between requirements and resources--including funding-- from the start and execute those programs using knowledge-based acquisition practices.
In our previous work, we have identified proven management practices--many of which have been incorporated into DOD policy, but have yet to be fully implemented in practice--that can serve as tools to prevent DOD cost overruns. Greater adherence to practices at key phases of the acquisition process can help reduce weapon system costs, contain pressures for increased funding, and better address critical warfighter needs
DEFENCE TALK: http://www.defencetalk.com/trends-in-nunn-mccurdy-cost-breaches-for-major-defense-acquisition-programs-33131/#ixzz1I9v0MGm1

No comments:

Post a Comment

DISCLAIMER : KOMENTAR DI BLOG INI BUKAN MEWAKILI ADMIN INDONESIA DEFENCE , MELAINKAN KOMENTAR PRIBADI PARA BLOGERSISTA
KOMENTAR POSITIF OK

BERITA POLULER

BACA JUGA: